A Citizen’s Guide for Construction Projects
*This is a guide only. If you have any questions, would like a complete copy of the Building By-laws pertaining to your project, or you would like a building permit application, please contact the Town Office @ 483-5200.
| Prior to commencement of any construction work, all residents, property owners or contractors are required to obtain a building permit. Applications for building permits, once accurately completed, will go to the Souris Town Council for final approval. Approval must be obtained from Council before work can begin. |
 |
|
 |
| |
 |
Information Required when Applying for a Building Permit
The owner or an agent of the owner must complete a building permit application form. Information on the application form includes:
- Identify and describe in detail the work being done (new, addition, alteration, renovation, repair, etc.)
- Describe the land on which the work is to be done by a description that will readily identify and locate the building lot. (A survey certificate showing the proper corner pegs on the lot.)
- In the case where there are pre-existing buildings on the land, a Building Location Certificate may be required to show the exact location of the buildings on the
property.
- State the value of the proposed work-Use and size of the building
- Construction information (materials being used)
- State the names, addresses and telephone numbers of the owners, architects, professional engineer or other designer, and contractors.
- Drawings must be submitted with the complete building permit application to show what will be built.
* The exact specifications for drawings are available at the Town Office.
- Any additional information required or requested by the Building Inspector
|
|
|
 |
|
 |
|
| |
| A Demolition Permit is required for the removal of any building, structure or portion of. |
 |
|
|
 |
 |
|
 |
| |
Fences
1.)
- (a) Fences may not exceed three feet in height in a front yard.
- (b) a fence must be set back 12 feet on the side site line on the street side of a corner site.
- (c) A fence cannot exceed seven feet in a side yard or rear yard. (With the exception of a corner yard as explained in 1.a. A fence must be built within your own property line. To ensure this is done correctly, the following is needed to build a fence in the Town of Souris:
- (A) A building permit (The Building Inspector will indicate if any information other than a survey certificate is required to obtain your permit.)
- (B) A survey certificate showing the corner pegs on the lot.
|
|
 |
|
 |
|
|
|
 |
 |
|
 |
| |
Commercial Buildings
All commercial building renovations, whether structural or not, will require you to contact the Building Inspector. 483-5200. |
|
 |
|
 |
|
|
| |
| |
|
|
 |
 |
 |